Revolution Wind reaches full commercial operation
Ørsted said on 5 November that its 704 MW Revolution Wind began generating up to full capacity in October, making it the third large US offshore wind farm in full commercial operation.

Ørsted said in an emailed statement after its quarterly earnings call on 5 November that Revolution Wind began generating up to its full capacity in October. The company said the project is delivering power under 20-year contracts with utilities in Rhode Island and Connecticut.
Revolution Wind has 65 turbines and 704 MW of capacity. It is about 15 miles south of Little Compton, Rhode Island, and is a 50-50 partnership between Ørsted and Skyborn Renewables, part of Global Infrastructure Partners. The project first sent power to the New England grid in March 2026, and crews installed the last of its 65 turbines in September. Installation was slowed by damage to a leg of an installation vessel in June 2025, which needed five weeks of inspection and repairs.
Ørsted says the project is "generating up to its full capacity" but has not published detailed output figures. The company's financial report showed the ramp-up: Ørsted's US offshore wind generation reached 240 GWh in the third quarter, compared with 50 GWh a year earlier.
Third large US offshore wind farm
Revolution Wind is the third large, commercial-scale US offshore wind farm in full operation, after South Fork Wind off New York and Vineyard Wind off Massachusetts. Vineyard Wind, the 800 MW Massachusetts project, reached full commercial operations in late October, WBUR reported.
The pipeline for future projects has shrunk. BloombergNEF once projected 39 GW of US offshore wind by 2035; it now expects 5.9 GW, Canary Media reported.
Contracts and savings
Rhode Island contracted for 400 MW and Connecticut for 304 MW under fixed-price, 20-year power purchase agreements, Ørsted said. Three utilities buy the power: Rhode Island Energy, Eversource Energy and United Illuminating, Canary Media reported.
Ørsted says the project can produce enough power for more than 350,000 New England homes. Connecticut's Department of Energy and Environmental Protection has estimated it would save New England ratepayers as much as $500 million a year in wholesale energy costs.
Stop-work orders and court challenge
Two federal stop-work orders delayed the project. BOEM issued the first on 22 August 2025, when Revolution Wind was about 80 percent complete. A federal court granted a preliminary injunction on 22 September 2025, and construction restarted.
A second order on 22 December 2025 paused work again, with seven turbines still to install. The US District Court for the District of Columbia granted another preliminary injunction on 12 January 2026.
The legal fight is not over. In October, the Interior Department asked a federal court for permission to reevaluate its 2023 approval of the project's construction and operations plan, a move that did not immediately affect project activities, Canary Media reported.
Sources
32- 01A third major US offshore wind farm is now fully operationalEN
- 02Ørsted Starts Commercial Operations on Its Second US Offshore Wind FarmEN
- 03Revolution Wind Enters Commercial Operations After Final Turbines InstalledEN
- 04Offshore Revolution Wind development is now fully operationalEN
- 05Eversource's financial risk eases as Revolution Wind hits full commercial operations: CEOEN
- 06Wind Power Project Trump Administration Tried To Halt Is Now Fully OperationalEN
- 07US Gets New Offshore Wind Farm as All Turbines Installed at 704 MW Revolution WindEN
- 08US Offshore Wind Project Revolution Wind Installs Last TurbineEN
- 09Revolution Wind installs final turbine; will be fully operational later this yearEN
- 10Vineyard Wind, the country's largest offshore wind project, is fully up and runningEN
- 11Three Ørsted Offshore Wind Farms Set for Full Commissioning in 2026 - Offshore WindEN
- 12Borkum Riffgrund 3, Ørsted’s largest offshore wind farm in Germany, produces first power - OrstedEN
- 13EVWORLD.COM - EVWORLD.COMEN
- 14Final wind turbine goes up for offshore wind farm targeted by TrumpEN
- 15Trump Is Gonna Cave On Offshore Wind In 5…4…3…EN
- 16Microsoft is winding down its deal to rent AI computing from OracleEN
- 17Microsoft Winding Down Oracle Deal to Rent AI Cloud CapacityEN
- 18 Northern lights could reach New York and Idaho this weekend as speedy solar wind races toward Earth EN
- 19Tesla to wind down Cybertruck production as Elon Musk focuses on robotics and AIEN
- 20Tesla is 'winding down' Cybertruck production at its Texas GigafactoryEN
- 21STAT+: After Medicare punts RPM overhaul to 2029, advocates see window to fight backEN
- 22Türkiye targets 175 GW of solar, wind capacity by 2040EN
- 23Electric Buses Need a Plan for the Next Operating ContractEN
- 24Nabrawind’s Crane-Free Wind Towers Face a Supplier TestEN
- 25 Open source project renders your Windows 11 desktop using the NPU rather than the GPU EN
- 26SLAC scientists find conclusive proof of a mysterious third type of magnetismEN
- 27Microsoft Paint RCE Fix Now Available, but Windows Update Won't Deliver ItEN
- 28CesiumAstro Secures $730 Million in Janus Henderson-Led Series D at a Valuation Above $4.5 Billion; Unveils Synchronicity Satellite Constellation Following FullEN
- 29Blue Origin unveils New Glenn GS3 third stage and Northstar booster engineEN
- 30Here’s how solar and wind developers can hold on to tax creditsEN
- 31Windows 11 can run better on PCs with 8GB now, Microsoft says – here’s whyEN
- 32FCC clears drone operations in 800MHz bandEN
All figures and quotations in this text come from the sources listed below.
Content prepared by the editorial team with AI assistance.
Comments
0- No comments yet — be the first.