Firmus's Long Reach data centre not fully funded, Tasmanian committee told
Firmus has not secured full funding for Long Reach, its largest planned Tasmanian data centre, general energy manager Paul Grzinic told a Tasmanian parliamentary committee, ABC News reported.

Funding status
Grzinic told Tasmania's parliamentary energy committee that the St Leonards site in Launceston was fully funded and that stage one of Wesley Vale was also fully funded. A company spokesperson said St Leonards was well advanced in construction and contracted to a customer. Wesley Vale stage one had funding allocated but was awaiting approval, the spokesperson said, while Bell Bay, the site of Long Reach, was under option to a customer and would be funded in stages. Firmus would not identify those customers.
Firmus is building a data centre at St Leonards in Launceston, has development approval for Long Reach, and is seeking approval for a third Tasmanian facility at Wesley Vale, ABC News reported. Long Reach is the largest of the three, with planned capacity of 288MW. The Bell Bay site would make Firmus Tasmania's largest electricity user, The Conversation reported. Firmus, led by co-chief executives Oliver Curtis and Tim Rosenfield, is Nvidia-backed. Its website says it has two sites operational and five under development across Australia, Singapore, Indonesia and Malaysia.
Power supply
Hydro Tasmania said it was assessing a Firmus request for 444MW, with a decision expected by the end of the year. It has identified three planned wind farms that could supply the company once operational, but said new generation would not be available until at least 2030.
Grzinic said all energy for Firmus's Tasmanian facilities would be developed and procured in Tasmania. He said consultants had mistakenly included incorrect information in a submission to a federal AI inquiry.
IPO withdrawal
Firmus withdrew its application to list on the Australian Securities Exchange on 9 October, after order books closed in Sydney that morning. The board cited recent market volatility and prevailing market conditions and said the terms would not appropriately reflect the business and its long-term growth outlook. The board concluded that proceeding with the offer was not in the best interests of the company and its shareholders. The float would have been Australia's largest since Telstra in 1997, ABC News reported.
Firmus said it would pursue private market funding and consider alternative public and private options. The company had planned to raise US$5.5 billion in the float, with proceeds needed to help fund construction of the broader network, The Straits Times reported.
Approvals
Firmus is appealing a George Town Council condition limiting the use of backup diesel generators at Long Reach. Latrobe Council has asked Planning Minister Kerry Vincent to consider the Wesley Vale proposal as a major project, ABC News reported. About 6,000 people signed a petition against the Bell Bay project, The Conversation reported.
Sources
39- 01Data centre operator Firmus pulls blockbuster ASX float after lacklustre demandEN
- 02Australia's Firmus withdraws planned A$7 billion stock market listingEN
- 03Nvidia-backed Firmus IPO being pulled sends AI funding warningEN
- 04$44b AI firm's float in ruins, investors let ripEN
- 05Firmus withdraws ASX listing application, set to pursue private capitalEN
- 06Oliver Curtis' bid to float Firmus for $44 billion falls overEN
- 07Firmus pulls its ASX listing as investors balk at AI infrastructure valuationEN
- 08Firmus pulls ASX IPO after 48 hours of weak demandEN
- 09Can data centre company Firmus live up to its blockbuster $43 billion listing value? Why some investors doubt itEN
- 10Firmus Funding Remains Incomplete for Tasmania Data CentreEN
- 11Firmus Technologies withdraws ASX IPO as investors question AI infrastructure riskEN
- 12Google takes over the Wyoming data centre site Crusoe had plannedEN
- 13Does the Democratic midterm victory spell the end of US AI data centre boom?EN
- 14Vensum Power raises €9M to cut power losses in AI data centres, EV charging and energy storageEN
- 15Aluminum–Air Generators for Data Centres Face a Metal Logistics TestEN
- 16The datacentre arms race hits pause in south-east AsiaEN
- 17Lanarkshire AI datacentre to fully rely on National Grid despite renewables claimEN
- 18Crusoe sells troubled Wyoming data center project to GoogleEN
- 19OpenAI will keep investing in AI data centers despite election results, CFO tells CNBCEN
- 20Several Democrats renew calls for datacenter pauses after blue waveEN
- 21All the latest updates on AI data centersEN
- 22Activists break into building site of Microsoft datacentre in AmsterdamEN
- 23Voters gave a big middle finger to data centersEN
- 24 Protesters storm Microsoft AI data center construction site EN
- 25Meta warns that election backlash against data centers could make AI expansion harderEN
- 26Voters rejected AI data centers over resource concerns. Here's why measuring water usage is hardEN
- 27Electric cars are about to overtake petrol in the UK, data showsEN
- 28OpenAI pledges to halt NDAs in new data center policy proposal after election rebukeEN
- 29LIV Golf set to close down after BC Partners withdraws US$300m lifelineEN
- 30SAP promises to open out data flows in both directionsEN
- 31Adding Network Security To AI, HPC, And Data CentersEN
- 32Texas was the new epicenter of the AI data center buildout. That might be kaput.EN
- 33More Than 100 Protesters Storm a Microsoft Data Center Site in AmsterdamEN
- 34Can Optical AI Cut Data Center Inference Power Use?EN
- 35AI-driven data centers: Revolutionizing decarbonization strategiesEN
- 36 AI data centers comprehensively defeated at US midterm elections EN
- 37Securing the agentic enterprise with data lineageEN
- 38Singapore Reveals Five-Year Energy Plan to Feed Data Center, Semicon ProgressEN
- 39Stratos Data Center Will Emit Air Pollution That’s Linked to Premature Deaths and Health Economic Damages for Utah & States DownwindEN
All figures and quotations in this text come from the sources listed below.
Content prepared by the editorial team with AI assistance.