Waterford council refuses Kilmeaden data centre permission

Waterford City and County Council refused planning permission on 15 October for a 108.79-hectare data centre and energy project at the former Kilmeaden cheese factory, a refusal campaigners called a victory.

TechnologyAnalysisGrace OkonkwoPublished: 6 November 20265 min readSources 36
Waterford council refuses Kilmeaden data centre permission

Waterford City and County Council refused planning permission on 15 October for the Kilmeaden data centre and energy development. The application from Crag Rathnew DC Limited and Kent Homes Limited covered the former Kilmeaden cheese factory site and adjoining lands, RTE reported.

The planning application stated the project would provide a mixed-use village centre, technology park and renewable energy development on 108.79 hectares. It proposed three ICT buildings each around 24,000 sq m, an energy centre with 16 gas-powered turbines, a solar farm with more than 43,000 panels and a battery energy storage system. The wider plan included 48 apartments, a two-storey supermarket with an off-licence, a childcare facility, a community centre, a gym, a cafe, a health centre and a pharmacy.

The Irish Examiner reported that major data centre developer Echelon was also behind the project. The developers said their facilities are designed and developed in line with regulatory guidelines and in consultation with community representatives, RTE reported.

The application

The Irish Examiner reported that the application was first submitted in September 2025. Waterford Live reported more than 500 submissions, the vast majority opposed. The village has approximately 300 residents, the Irish Examiner reported.

Sinn Féin TD Conor McGuinness said the development would have had an average electricity demand of approximately 203 megawatts. He said it was not a minor development and argued that projects of that scale must be assessed on their full environmental and infrastructure impacts, Waterford Live reported.

McGuinness and party colleague David Cullinane welcomed the refusal, as did councillors John O'Leary, Catherine Burke and Declan Clune, Waterford News reported. Both TDs had opposed the project, Waterford Live reported. Cullinane said Ireland needs a coherent approach to data centres that takes account of electricity demand, grid capacity, climate obligations and the impact on local communities.

The campaign

RTE reported on 10 October that over 300 people took part in a slow drive protest through Kilmeaden. Cars, tractors and vans set off from Ballyduff National School. Waterford News put a similar drive-slow protest on Sunday 11 October at around 300 people.

Amanda Power, a committee member of the Kilmeaden Against Industrialisation group, told RTE that if the development were built "there's no going back". Danny Brennan, who has lived on the border of the site for over 50 years, said the data centres would sit at the bottom of his garden and that the house would be worth nothing.

Friends of the Earth Ireland says data centres now use 23% of all electricity in Ireland, a share it calls unprecedented globally. The group says the proliferation of data centres is increasing energy bills and locking Ireland into a new generation of fossil fuels, the Munster Express reported.

The Munster Express also reported that, by the developers' own calculations, the planned solar farm would have covered only 2% of the data centres' energy needs.

What happens next

Waterford Live reported that the Notification of Decision letter had not been uploaded to the council website, leaving the official reasons for the refusal unknown. That leaves the grounds for any appeal unclear.

Power told the Munster Express that the refusal could still be appealed and that the campaign was not over. She called for a national moratorium on new data centres until rules are put in place on where they can be built, how many are needed and whether infrastructure can support them.

The Munster Express reported that Waterford residents will join a Dublin demonstration on Saturday 7 November, starting at noon from the Garden of Remembrance. It said the event is part of a European day of action on data centres, organised by Friends of the Earth Ireland with community groups, with more than 85 groups from ten countries taking part.

Comments 0

Sources

36
  1. 01Planning permission for major data centre development in Co Waterford refusedEN
  2. 02Kilmeaden Residents Stand Against New Data Centre Building Proposal In Rural IrelandEN
  3. 03Waterford Council refuses planning permission for major Kilmeaden data centreEN
  4. 04Victory for Kilmeaden community as mega Waterford data centre refused permissionEN
  5. 05Permission refused for controversial data centre planned for Waterford villageEN
  6. 06Major Kilmeaden development is refusedEN
  7. 07Residents protest against major data centre development in WaterfordEN
  8. 08Waterford to take part in national protest against data centresEN
  9. 09‘Massive boost’ for campaign against development of new data centre in WaterfordEN
  10. 10Google’s first Wyoming data centre will run on gas with carbon captureEN
  11. 11Aluminum–Air Generators for Data Centres Face a Metal Logistics TestEN
  12. 12Activists across Europe prepare two days of protests against datacentresEN
  13. 13OpenAI is stepping back from NDAs for data center projectsEN
  14. 14Meta warns that election backlash against data centers could make AI expansion harderEN
  15. 15Voters rejected AI data centers over resource concerns. Here's why measuring water usage is hardEN
  16. 16Voters rebuff data centers in every ballot measure except one during the 2026 midtermsEN
  17. 17Data Centres Take 23% of Irish Power, Podcast Says [2026] - tech-insider.orgEN
  18. 18Electric cars are about to overtake petrol in the UK, data showsEN
  19. 19OpenAI pledges to halt NDAs in new data center policy proposal after election rebukeEN
  20. 20SAP promises to open out data flows in both directionsEN
  21. 21Adding Network Security To AI, HPC, And Data CentersEN
  22. 22After the midterms, a bigger clash over data centers could be comingEN
  23. 23The Blue Wave Has Tech Bros Scrambling for Data Centers in SpaceEN
  24. 24Texas was the new epicenter of the AI data center buildout. That might be kaput.EN
  25. 25The Results Are In: Voters Hate Data CentersEN
  26. 26HuBMAP Updates Data Portal for Studying Human Tissues at Single-Cell ResolutionEN
  27. 27Google to serve as credit backstop for TeraWulf data center in KentuckyEN
  28. 28Cork Takes the Heat So DRACO’s Data Can SurviveEN
  29. 29 AI data centers comprehensively defeated at US midterm elections EN
  30. 30Securing the agentic enterprise with data lineageEN
  31. 31Singapore Reveals Five-Year Energy Plan to Feed Data Center, Semicon ProgressEN
  32. 32Adding Network Security to AI, HPC and Data CentersEN
  33. 33Stratos Data Center Will Emit Air Pollution That’s Linked to Premature Deaths and Health Economic Damages for Utah & States DownwindEN
  34. 34Ukraine’s drone strikes spur hasty Russian plans for underground data centersEN
  35. 35 OpenAI introduces program to reduce AI data center energy demand during peak hours EN
  36. 36 8 converted jet engines are powering xAI data centers as companies look for new energy sources EN

All figures and quotations in this text come from the sources listed below.

Content prepared by the editorial team with AI assistance.

Grace Okonkwo

Grace Okonkwo

AI, models and technology

Grace Okonkwo covers AI, models and technology for FLASH24, working from primary sources such as model cards, API documentation and benchmark papers rather than vendor summaries. She checks training data provenance, evaluation conditions and reported scores against the underlying datasets before any figure reaches print. She interviews researchers and engineers directly, tracks release calendars from major labs, and compares successive model versions on the same tests. Her own self-hosting, home-network and documentation-reading habits feed straight into that desk, since she tests tools on her own hardware first. She does not publish benchmark claims without a reproducible method.

Newsroom →

Comments

0
  1. No comments yet — be the first.

Write a comment

Comments are public. We do not publish abuse, spam or advertising.